Software Project Tracking and Oversight
a key process area for level 2: Repeatable
The purpose of Software Project Tracking and Oversight is to provide adequate
visibility into actual progress so that management can take effective actions
when the software project's performance deviates fe3 significantly from
the software plans.
Software Project Tracking and Oversight involves tracking and reviewing
the software accomplishments and results against documented estimates,
commitments, and plans, and adjusting these plans based on the actual
accomplishments and results.
A documented plan for the software project (i.e., the software development
plan, as described in the Software Project Planning key process area)
is used as the basis for tracking the software activities, communicating
status, and revising plans. Software activities are monitored by the management.
Progress is primarily determined by comparing the actual software size,
effort, cost, and schedule to the plan when selected software work products
are completed and at selected milestones. When it is determined that the
software project's plans are not being met, corrective actions are taken.
These actions may include revising the software development plan to reflect
the actual accomplishments and replanning the remaining work or taking
actions to improve the performance.
Goals
Goal 1
Actual results and performances are tracked against the software plans.
Goal 2
Corrective actions are taken and managed to closure when actual results
and performance deviate significantly from the software plans.
Goal 3
Changes to software commitments are agreed to by the affected groups and
individuals.
Commitment to perform
Commitment 1 -- A project software manager is designated to be responsible
for the project's software activities and results.
Commitment 2 -- The project follows a written organizational policy
for managing the software project.
This policy typically specifies that:
- A documented software development plan is used and maintained as
the basis for tracking the software project.
- The project manager is kept informed of the software project's status
and issues.
- Corrective actions are taken when the software plan is not being
achieved, either by adjusting performance or by adjusting the plans.
- Changes to the software commitments are made with the involvement
and agreement of the affected groups.
Examples of affected groups include:
- software engineering (including all subgroups, such as software
design),
- software estimating,
- system engineering,
- system test,
- software quality assurance,
- software configuration management,
- contract management, and
- documentation support.
- Senior management reviews all commitment changes and new software
project commitments made to individuals and groups external to the organization.
Ability to perform
Ability 1 -- A software development plan for the software project is
documented and approved.
Refer to Activities 6 and 7 of the Software Project Planning key process
area for practices covering the software development plan.
Ability 2 -- The project software manager explicitly assigns responsibility
for software work products and activities.
The assigned responsibilities cover:
- The software work products to be developed or services to be provided.
- The effort and cost for these software activities.
- The schedule for these software activities.
- The budget for these software activities.
Ability 3 -- Adequate resources and funding are provided for tracking
the software project.
- The software managers and the software task leaders are assigned
specific responsibilities for tracking the software project.
- Tools to support software tracking are made available.
Examples of support tools include:
- spreadsheet programs, and
- project planning/scheduling programs.
Ability 4 -- The software managers are trained in managing the technical
and personnel aspects of the software project. 19d
Examples of training include:
- managing technical projects;
- tracking and oversight of software size, effort, cost, and schedule;
and
- managing people.
Ability 5 -- First-line software managers receive orientation in the
technical aspects of the software project.
Examples of orientation include:
- the project's software engi fe1 neering standards and procedures,
and
- the project's application domain.
Activities performed
Activity 1 -- A documented software development plan is used for tracking
the software activities and communicating status.
Refer to Activity 7 of the Software Project Planning key process area for
practices covering the content of the software development plan.
This software development plan is:
- Updated as the work progresses to reflect accomplishments, particularly
when milestones are completed.
- Readily available to:
- the software engineering group (including all subgroups, such
as software design),
- the software managers,
- the project manager,
- senior management, and
- other affected groups.
Activity 2 -- The project's software development plan is revised according
to a documented procedure.
Refer to Activity 6 of the Software Project Planning key process area for
practices covering the activities for producing the software development
plan.
This procedure typically specifies that:
- The software development plan is revised, as appropriate, to incorporate
plan refinements and incorporate plan changes, particularly when plans
change significantly.
Interdependencies between the system requirements allocated to software,
design constraints, resources, costs, and schedule need to be reflected
in all changes to the plan.
- The software development plan is updated to incorporate all new software
project commitments and changes to commitments.
- The software development plan is reviewed at each revision.
- The software development plan is managed and controlled.
"Managed and controlled" implies that the version of the work product
in use at a given time (past or present) is known (i.e., version control),
and changes are incorporated in a controlled manner (i.e., change control).
If a greater degree of control than is implied by "managed and controlled"
is desired, the work product can be placed under the full discipline
of configuration management, as is described in the Software Configuration
Management key process area.
Activity 3 -- Software project commitments and changes to commitments
made to individuals and groups external to the organization are reviewed
with senior management according to a documented procedure.
Activity 4 -- Approved changes to commitments that affect the software
project are communicated to the members of the software engineering group
and other software-related groups.
Examples of other software-related groups include:
- software quality assurance,
- software configuration management, and
- documentation support.
Activity 5 -- The size of the software work products (or size of the
changes to the software work products) are tracked, and corrective actions
are taken as necessary.
Refer to Activity 9 of the Software Project Planning key process area for
practices covering derivation of size estimates.
- Sizes for all major software work products (or the size of the changes)
are tracked.
- Actual size of code (generated, fully tested, and delivered) is compared
to the estimates documented in the software development plan.
- Actual units of delivered documentation are compared to the estimates
documented in the software development plan.
- Overall projected size of the software work products (estimates combined
with actuals) is refined, monitored, and adjusted on a regular basis.
- Changes in size estimates of the software work products that affect
software commitments are negotiated with the affected groups and are
documented.
Activity 6 -- The project's software effort and costs are tracked, and
corrective actions are taken as necessary.
Refer to 195 Activity 10 of the Software Project Planning key process area
for practices covering the derivation of cost estimates.
- Actual expenditures of effort and costs over time and against work
completed are compared to the estimates documented in the software development
plan to identify potential overruns and underruns.
- Software costs are tracked and compared to the estimate fdb s documented
in the software development plan.
- Effort and staffing are compared to the estimates documented in the
software development plan.
- Changes in staffing and other software costs that affect software
commitments are negotiated with the affected groups and are documented.
Activity 7 -- The project's critical computer resources are tracked,
and corrective actions are taken as necessary.
Refer to Activity 11 of the Software Project Planning key process area for
practices covering the derivation of computer resource estimates.
- The actual and projected use of the project's critical computer resources
are tracked and compared to the estimates for each major software component
as documented in the software development plan.
- Changes in estimates of critical computer resources that affect software
commitments are negotiated with the affected groups and are documented.
Activity 8 -- The project's software schedule is tracked, and corrective
actions are taken as necessary.
Refer to Activity 12 of the Software Project Planning key process area for
practices covering derivation of the schedule.
- Actual completion of software activities, milestones, and other commitments
is compared against the software development plan.
- Effects of late and early completion of software activities, milestones,
and other commitments are evaluated for impacts on future activities
and milestones.
- Software schedule revisions that affect software commitments are
negotiated with the affected groups and are documented.
Activity 9 -- Software engineering technical activities are tracked,
and corrective actions are taken as necessary.
- Members of the software engineering group report their technical
status to their first-line manager on a regular basis.
- Software release contents for successive builds are compared to the
plans documented in the software development plan.
- Problems identified in any of the software work products are reported
and documented.
- Problem reports are tracked to closure.
Activity 10 -- The software risks associated with cost, resource, schedule,
and technical aspects of the projectare tracked.
Refer to Activity 13 of the Software Project Planning key process area for
practices covering identification of risks.
- The priorities of the risks and the contingencies for the risks are
adjusted as additional information becomes available.
- High-risk areas are reviewed with the project manager on a regular
basis.
Activity 11 -- Actual measurement data and replanning data for the software
project are recorded.
Refer to Activity 15 of the Software Project Planning key process area for
practices covering recording of project data.
- Information recorded includes the estimates and associated information
needed to reconstruct the estimates and verify their reasonableness.
- The software replanning data are managed and controlled.
- The software planning data, replanning data, and the actual measurement
data are archived for use by ongoing and future projects.
Activity 12 -- The software engineering group conducts periodic internal
reviews to track technical progress, plans, performance, and issues against
the software development plan.
These reviews are conducted between:
- The first-line software managers and their software task leaders.
- The project software manager, first-line software managers, and other
software managers, as appropriate.
Activity 13 -- Formal reviews to address the accomplishments and results
of the software project are conducted at selected project milestones according
to a documented procedure.
These reviews:
- Are planned to occur at meaningful points in the software project's
schedule, suc 196 h as the beginning or completion of selected stages.
- Are conducted with the customer, end user, and affected groups within
the organization, as appropriate.
The end users referred to in these practices are the customer designated
end users or representatives of the end users.
- Use materials that are reviewed and approved by the responsible software
managers.
- Addr f94 ess the commitments, plans, and status of the software activities.
- Result in the identification and documentation of significant issues,
action items, and decisions.
- Address the software project risks.
- Result in the refinement of the software development plan, as necessary.
Measurement and analysis
Measurement 1 -- Measurements are made and used to determine the status
of the software tracking and oversight activities.
Examples of measurements include:
- effort and other resources expended in performing the tracking and
oversight activities; and
- change activity for the software development plan, which includes
changes to size estimates of the software work products, software cost
estimates, critical computer resource estimates, and schedule.
Verifying implementation
Verification 1 -- The activities for software project tracking and oversight
are reviewed with senior management on a periodic basis.
The primary purpose of periodic reviews by senior management is to provide
awareness of, and insight into, software process activities at an appropriate
level of abstraction and in a timely manner. The time between reviews should
meet the needs of the organization and may be lengthy, as long as adequate
mechanisms for exception reporting are available.
- The technical, cost, staffing, and schedule performance are reviewed.
- Conflicts and issues not resolvable at lower levels are addressed.
- Software project risks are addressed.
- Action items are assigned, reviewed, and tracked to closure.
- A summary status report from each meeting is prepared and distributed
to the affected groups.
Verification 2 -- The activities for software project tracking and oversight
are reviewed with the project manager on both a periodic and event-driven
basis.
- Affected groups are represented.
- The technical, cost, staffing, and schedule performance is reviewed
against the software development plan.
- Use of critical computer resources is reviewed; current estimates
and actual use of these critical computer resources are reported against
the original estimates.
- Dependencies between groups are addressed.
- Conflicts and issues not resolvable at lower levels are addressed.
- Software project risks are addressed.
- Action items are assigned, reviewed, and tracked to closure.
- A summary report from each meeting is prepared and distributed to
the affected groups.
Verification 3 -- The software quality assurance group reviews and/or
audits the activities and work products for software project tracking
and oversight and reports the results.
Refer to the Software Quality Assurance key process area.
At a minimum, the reviews and/or audits verify:
- The activities for reviewing and revising commitments.
- The activities for revising the software development plan.
- The content of the revised software development plan.
- The activities for tracking the software project's cost, schedule,
risks, technical and design constraints, and functionality and performance.
- The activities for conducting the planned technical and management
reviews.
|
|